What is complete and work complete in MS Project?

What is complete in MS Project?

The % Complete fields contain the current status of a task, expressed as the percentage of the task’s duration that has been completed. You can enter percent complete, or you can have Project calculate it for you based on actual duration.

How is work complete calculated in MS Project?

Percent Complete is a measure based on duration and Percent Work Complete is based on work. The two fields are calculated as follows: Percent Complete = Actual Duration/Duration (PC=AD/D) Percent Work Complete = Actual Work/Work (PWC=AW/W)

What is the difference between work and duration in MS Project?

Effort (also referred to as Work) is the actual time required to complete the task. Duration is the total amount of time in which the user has to complete the task. For example, you might have a task that only takes 2 hours to physically complete, but that task can be completed anytime over the next week.

How do you complete in Microsoft Project?

Update tasks to 100% complete for the current or status date

  1. On the Task tab, in the View group, choose Gantt Chart.
  2. Hold CTRL and select each of the tasks in the list that you want to update. …
  3. In the Schedule group, choose 100% Complete.
THIS IS FUNNING:  How much do home project managers make?

What is the difference between complete and physical complete in MS Project?

Physical Percent (%) Complete (task field)

Unlike the % Complete field, the Physical % Complete field is independent of the total duration or actual duration values used by the % Complete field to calculate BCWP. … However, you only spent 75 of 150 minutes, so in terms of duration, the job is only 50 percent complete.

How do you calculate completed?

Divide your Successfully Completed Credit Hours by your Attempted Credit Hours. If the resulting percentage is 67% or greater, then you have met the 67% Completion Standard for financial aid. Example: 19 Successfully Completed Hours ÷ 27 Attempted Credit Hours = . 703 or 70% (Note: Do not round numbers up or down.)

What’s the difference between complete and completed?

2 Answers. Complete, unlike completed, implies something whole or full. Completed means finished, accomplished, or done. A lot of the meaning overlaps, but I think completed gives a better sense of accomplishment, though it really depends on how you’re using it.

What is the difference between fixed units and fixed duration?

The difference between fixed units and fixed duration can be seen when modifying the units and work for a task. For Fixed units tasks, when revising units and work -duration is recalculated. For fixed duration tasks, when revising units – work is recalculated and when revising work-units are recalculated.

What is the duration of work?

Duration of the Work means the number of Days from a Job Order notice to proceed to Substantial Completion. Sample 2.